Cases
Rep Matters: Represented Connecticut Department of Transportation in negotiations for
award of the public private partnership agreement for the redevelopment, operation
maintenance of service plaza facilities along I-395, I-95
Route 15 in Connecticut.
Represented Connecticut Resources Recovery Authority for Procurement negotiations
award of Operation & Maintenance Agreement for the waste to energy facility in Hartford, CT.
Represented contractor in negotiations with Northeast Utilities for $20M agreement for 345kV underground cable transmission project.
Represented a general contractor
surety against delay claims
project specification
design issues on a $25M project at Bradley Airport
Multifaceted Health Care Development
Construction Deal Negotiated, Documented,
Closed
Halloran & Sage successfully counseled a large Connecticut construction
real estate firm through the negotiation, documentation,
closing of the development
construction a new health care facility
an adjacent medical office building. The project involved the negotiation
preparation of a participation agreement, a purchase
sale transaction, reciprocal easement agreements, construction contracts
leases. Additionally, Halloran & Sage represented its client in securing
documenting $19,500,000 of construction financing.
The Halloran & Sage team was led by real estate partner James Maher
also included real estate associates Matthew Teich, Jaimee Newman
Casey O'Connell, construction partner William Wilson, II,
legal assistant Karel Ortolani.
Represent Owner
Construction Manager in the development
construction of a Cancer Center
Medical Office Building
Represented a construction manager
owner on construction
design issues that arose on a $125 Million project for the renovation of a historic theater
the construction of a new school in Waterbury, CT
Represented a private university against an architect on a claim for damages
repair costs of a defective flooring system
Represented a barge transportation company against State of Connecticut claim for damages
repair costs to a bridge fender system on the Norwalk River
Defense of a multi-party, multi-million dollar subrogation action brought against an architect
other design professionals for negligent design
installation of a fire suppression system
Defense of a professional negligence claim brought by an owner against a design professional (architect) for additional project costs allegedly related to design errors, lack of coordination
failed communication
Negotiated settlements between an environmental consultant, a Town
various subcontractors arising from the release of asbestos on an elementary school rehabilitation project
Representation of a private university on a claim involving a defective flooring system that was discovered after construction was completed. We worked with both the contractor
the architect to investigate the cause of the cracking
to replace the floor without resorting to litigation
H & S Counsels Lead Lender in $70M Luxury Hotel
Condo Deal
Halloran & Sage recently completed closing of a $70M construction loan facility for the luxury Ocean House Hotel
Condominium located in Westerly, Rhode Isl
. The firm served as counsel to U.S. Bank National Association, as lead lender for the bank group providing the financing. This project involves the complete renovation of an historic beachfront hotel into a 48 room luxury hotel with 24 residential condominium units. The Halloran & Sage team was led by real estate partner, James Maher
included construction partner, Bill Wilson, real estate associate, Jaimee Newman
legal assistant, Karel Gargiulo.